Projects: Rail

WPD

Western Power Distribution Under-Track Crossing Installations at Weston Super Mare

The objective was to execute a UTX for WPD at two separate substations by constructing a thrust and drive pit for auger boring to commence. This would all be completed whilst keeping the track live.

BCM Liverpool Street

Liverpool Street Station Platform Extension GRIP 5-8 Design & Build

The key project deliverable is to complete the platform extensions and associated works by 31st May 2021 to ensure our client can fully introduce and operate their new rolling stock.

Feltham Re-signalling Programme – Phase 1 & 2 Civils

BCM Construction were awarded the Principal Contractors role for the Design and Construction of the full civil engineering scope of works for the Feltham Resignalling Project Phase 2 and residual Phase 1. This multi-disciplinary project covers over 60 miles in total.

Thameslink Minor Works Framework

BCM Construction won the Thameslink Minor Civils Framework Contract to design and execute lineside engineering activities to facilitate the installation of other contractors’ equipment.

TRP E&P Resilience Programme

BCM Construction were hired by Network Rail to survey electrical assets along with installing ramp end shrouding and replacing lugs on jumper cables. These works took place between London Victoria Station to Balham Station, North Dulwich to Eastfeild and Earlswood to Preston Park.

Tunbridge Wells Power Supply Enhancement

The objective of the overall project is to improve system resilience and prevent further equipment failures between Tonbridge and Tunbridge Wells which have been caused by the introduction of 12-car electric train formations to Tunbridge Wells.

Great Western Route Modernisation: Design & Installation

This project was part of the well-known Great Western Electrification Programme. BCM were contracted by Network Rail to Design and Install a HV Independent Feeder cable between the new substations at Royal Wootton Bassett ATFS and Thingley Junction ATFS.

Crossrail Platform Extensions

Crossrail is a multi billion pound transport infrastructure scheme, delivering a new 118-kilometre (73-mile) railway line to London and the Home Counties of Berkshire, Buckinghamshire and Essex. In 2015, BCM were awarded a prestigious contract to complete the civil engineering

Sussex PSU – ETE WORKS – Victoria to Balham

The primary objective of this scheme is to ensure that there is sufficient DC traction power across Network Rail’s (NR) Sussex Route to meet the demands of the new December 2018 timetable, which will include a newer fleet and more frequent trains, all in accordance with the requirements of the Department of Transport’s (DTT) strategic plan.

In 2016, BCM were awarded a contract by Network Rail to complete the Electrical Track Equipment (ETE) works from Victoria to Balham. Working as their Principal Rail Contractor, BCM have faced a challenging access regime within these inner London sites, working on some of the busiest and most congested lines in the UK.

CP5 Electrification and Plant (E&P) Framework

In 2014, BCM fought off stiff competition to secure a five-year framework on behalf of Network Rail Infrastructure Projects (NR), to deliver electrification and plant upgrades and renewals in the Southern region.

Scroll Up